Daily Report
The Daily Report automatically generates daily entries for inductions, plant, and observations, helping subcontractors record accurate site activity.
As a Primary Contact or Nominated Representative, you can:
- Advise if your company is on or off site
- Record number of workers and visitors
- Update worker hours
- Submit a daily progress report
- Upload progress photos
- View observations raised
Submit Today’s Numbers and Progress
1. Log into HammerTech and select your project.
2. Go to Daily Report > Today’s Progress.
3. Enter:
- Number of workers on site
- Number of visitors (non-inducted one-off attendees)
- Total hours worked (e.g. 7am–3pm = 8 hours)
- Daily progress notes
4. (Optional) Upload progress photos.
5. Click Save Changes.
Tip: Submit updates daily to give site management a clear record of subcontractor progress and workforce numbers.